The Project

An innovative project in terms of its architecture and its environmental considerations, the redevelopment of the Jean Bouin Stadium will increase its seating capacity from 9,000 to 20,000. Enveloped in a fine mesh of fibre-reinforced concrete designed to minimise the visual impact on local residents, the stadium utilises energy-efficient, low-carbon materials and incorporates solar panels to meet its energy needs. The works, carried out in an urbanised area, include the demolition and reconstruction of the stadium and the creation of a car park.

The Scope of Work

For this project, setec opency undertook the following tasks: project management for design and construction, client support, and management of shared site expenditure.

Reconstruction du stade Jean Bouin

Expertises

Key figures

Project cost : €90 million

Construction period : 2009–2013