Architect: JP. Pargade
The project involves the demolition and subsequent reconstruction of the hospital’s south wing, covering 24,000 m², and the refurbishment of the central block, covering 22,000 m². Carried out whilst the site remains in use, the works involve numerous complex operations: relocation of equipment (technical platform, generators, MRI scanners, etc.), and the installation of temporary facilities (security control centre, canteen, patient admission area, etc.). The site remains accessible to the fire service throughout the project, and asbestos removal work is carried out during each phase of the works.
For this project, setec opency undertook the following roles: project management contractor, site management and client support.
Project cost : €69.5 million
Construction period : 2006–2015